TxDOT logoTYLER – Here’s a look at work planned in the district during the Week of August 3. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.

SMITH COUNTY – Tyler Maintenance crews are joined by one of the Special Jobs crews this week to conduct seal coat operations on I-20 service roads and overpasses at Joy Wright Mountain Road, Philpot Road and Howell Lake Road. A second crew on Monday continues base repairs on State Highway 135 between Troup and Arp but on Tuesday moves to Toll 49 just south of Interstate Highway 20. On Wednesday, the crew returns to State Highway 135. Expect the work at each of these locations to be reduced to one lane with flaggers providing traffic control.

Smith County construction projects updates:
Loop 323 West Widening
*Limits: Tyler’s West Loop and SH 31
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $12 million
More night work is planned for this widening and bridge replacement project on Tyler’s West Loop. The project is in full swing with an expected completion date in early 2016. The contractor last week placed the steel beams for the permanent bridge and is currently working on the retaining walls on both sides of the roadway as well as a hot mix application on the east side of the road as part of a temporary detour.

Loop 323 Northeast Project

*Limits: From American Legion Road (@ the Loop 323 Extension to US 271) south to Commerce St.
*Contractor: Reynolds and Kay, LTD.
*Cost: $3.4 million
This project includes culvert extensions, base repair, level-up and placing an overlay. Culvert work continues. Expect shoulder closures. The project should be completed in November 2015.

State Highway 31E Widening Project
*Limits: From FM 757 to FM 2012
*Contractor: Reynolds & Kay, LTD
*Cost: $7.8 million
Work on structures and embankment is ongoing in the eastbound lanes of this project to add passing lanes for multiple sections of roadway in both the eastbound and westbound directions. Once the widening is complete, a seal coat and final surface will be applied. Motorists should expect delays and shoulder closures as wells as a daily construction speed limit of 60 mph when work is being performed on this 18-month job.

State Highway 31E Widening Project
*Limits: From FM 850 to FM 757
*Contractor: East Texas Bridge, Inc.
*Cost: $3.4 million
This portion of SH 31E from FM 850 east of Tyler to FM 757 is being widened to add passing lanes for multiple sections of the roadway in both directions. The new
passing lanes are open to traffic and the project is nearing completion.

Off-System Bridge Replacement Project
*Limits: County Road (CR) 46 at Prairie Creek Tributary
*Contractor: East Texas Bridge, Inc.
*Cost: $490,000
The new bridge is completed and CR 46 is open to traffic. Final inspections continue as project winds down.

Off-System Bridge Replacement Project
*Limits: County Roads (CR) 452 and 481
*Contractor: Pierce Construction
*Cost: $560,000
Both roads are closed to through traffic with the contractor pouring the concrete deck on CR 452 later in the week as well as pouring traffic rail on CR 481. Motorists must use alternate routes to reach their destinations. The work is expected to be completed and the roads opened to traffic in October 2015.

State Highway 64
*Limits: from Chapel Hill to Arp
*Contractor: Drewery Construction of Nacogdoches
*Cost: $3.9 million
Work on the passing lanes between FM 2607 and Arp is underway. TxDOT reminds motorists to use extra caution and to watch for flaggers and a pilot car providing traffic control through this work zone. The Super 2 widening project continues and consists of clearing and grading. Current work includes cement treating subgrade and placing flex base for the passing lanes between FM 2607 and Arp. The daily speed zone reduction is posted at 60 mph when workers are present. Expect delays and traffic control conducted by flaggers and a pilot car.

Farm Road 850 Resurfacing Project
*Limits: 0.445 miles southeast of FM 2607 to the Rusk County line in Overton
*Contractor: Drewery Construction of Nacogdoches
*Cost: $2.1 million
Edge work and striping are being conducted on this project which consists of resurfacing the roadway by placing an overlay from FM 2607 to SH 135 in Overton. Flaggers and a pilot car are providing traffic control. Expect lane closures and delays as the project wraps up mid-week.

GREGG COUNTY – Longview Maintenance crews are back on Farm Road 2204/Stone Road placing an overlay between Farm Road 2011 traveling west to Farm Road 2276. The roadway will be reduced to one lane with flaggers providing traffic control. Expect delays in this location for the next couple of weeks.

Gregg County construction projects updates:
Spur 63 (McCann Road) at Guthrie Creek
*Limits: approximately 0.1 mile north and south of Guthrie Creek
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $435,000
This emergency repair contract will restore and stabilize the box culvert and its wing walls at Guthrie Creek. Expect daytime lane closures after 9 a.m. Work should be completed in August 2015.

Interstate Highway20 Total Maintenance Contract
*Limits: Gregg, Smith and Van Zandt counties
*Contractor: Fireman Excavating
Work is resuming this week in Van Zandt County where hot mix is being milled with closures in both the eastbound and westbound lanes. Also, on I-20 at SH 42 in Gregg County, the westbound exit and entrance ramp will be closed Monday night for mill and inlay operations. Tuesday night, the eastbound exit and entrance ramp for SH 42 will be closed for the same work.

State Highway 31 Landscape Project
*Limits: 0.3 miles north of FM 2205 (Grace Creek) to 0.2 miles south of U.S. 80 (Cotton) in Longview
*Contractor: South Texas Illuminations, LLC
*Cost: $281,249.70
Work is underway but should not impact traffic on this project which comes as a result of the city winning one of 10 Governor’s Community Achievement Awards presented by Keep Texas Beautiful in partnership with TxDOT, which allocates $2,000,000 a year as landscape incentives to competing communities based on population and efforts in litter prevention and cleanup, public awareness, beautification and property improvement, solid waste management, illegal dumping and enforcement, and education.

Farm Road 2275 George Richey Extension (Segments II & III)
*Limits: McCann Road to U.S. 259
*Contractor: East Texas Bridge, Inc.
*Cost: $12.8 million
Clearing between Judson and Airline roads continues with excavation, embankment, bridge construction, subgrade treatment, storm drain and other work between McCann and Judson roads. The contractor recently began paving operations. While this is a new location project that generally doesn’t impact traffic motorists should plan to take other routes to get around Airline Road is closed through March 2016.

Loop 281 at Farm Road 2087 Overpass
*Limits: SH 31 to approximately one mile south of SH 31
*Contractor: Longview Bridge and Road, Ltd., of Longview.
*Cost: $13.2 million
This project is in Phase III of construction with traffic moved off the existing loop onto the detours. The contractor is forming and pouring bridge rail. Expect delays during the peak evening hours. Caution advised in detour areas.

State Highway 42
*Limits: From SH 31 north to I-20
*Contractor: Reynolds & Kay, Ltd.
*Cost: $3.7 million
The contractor is constructing a left turn lane at Hillcrest Road along with storm drain and curb and gutter. Work is occurring behind the existing curb with minimal impact to traffic. The majority of the work will be conducted at night and should be finished in early fall. Use caution in this and all work zones.

Interstate Highway 20 Dynamic Message Signs (DMS)
*Locations
*East of FM 1255 westbound – Van Zandt County
*West of FM 849 eastbound – Smith County
*Derrick Park westbound – Smith County
*Contractor: Highway Intelligent Traffic Solutions Corp.
Final testing of these signs continues. There is sporadic impact to traffic as this
project nears completion.

Interstate Highway 20 PFC Project
*Limits: SH 31E to the Harrison County line
*Contractor: Madden Contracting Company, LLC
*Cost: $5,584,277
This project consists of applying a porous friction course (PFC) surface overlay, shoulder texturing, and pavement markings as well as work on the I-20 on ramps. Work this week will occur in the westbound mainlanes from the Harrison County line to the Sabine River. Motorists should expect lane closures and use alternate routes to reach their destinations.

Porous friction courses (PFC) consist of placing hot mix asphalt mixtures at the surface of a pavement structure in a thin layer to produce benefits for the traveling public such as safety, economy and the environment.

Anderson County construction projects updates:
U.S. Highway 79 New Lane Construction
*Limits: 1.6 miles southwest of Loop 256 in Palestine south to .4 mile southwest of FM 645
*Contractor: Longview Bridge and Road, Ltd., of Longview.
*Cost: $42,740,365.19
The contractor is excavating and hauling dirt on the south end of the project. Work is underway to prepare the section on the northbound travel lane of the Sanderson Farms intersection for concrete paving. No traffic delays are expected during this work.

U.S. Highway 79 – Night Work Repairs
*Limits: Loop 256 in Palestine southwest to 1.4 miles southwest of FM 1990 (Tile Factory Road)
*Contractor: Big Creek Construction of Hewitt, TX
*Cost: $2,374,737.51
This work will be conducted at night starting Tuesday, Aug. 4 and requires closing the roadway from 7 p.m. to 6 a.m. each night through Thursday. Going forward, starting the following week work is slated for Thursday through Sunday nights each week for the duration of the project. The roadway will be closed from 7 p.m. to 6a.m.

State Highway 19 in Anderson County
*Limits: 3.6 miles north of FM 837 (Henderson Co. line) south to .4 mile north of FM 321 at Montalba
*Contractor: Big Creek Construction of Hewitt
*Cost: $12,487,715.87
Contractor will be performing flex base and cement treat operations. Expect lane closures and delays.

Off-System Bridge Replacement Project
*Limits: County Road (CR) 453 at Beaver Creek
*Contractor: Highway 19 Construction of Sulphur Springs, Texas
*Cost: $256,312.87
CR 453 remains closed at Beaver Creek as a new bridge is built. Motorists must use alternate routes to reach their destinations. This project will be completed in August 2015.

Off-System Bridge Replacement Project
*Limits: County Road (CR) 471 at Box Creek
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $817,412.15
CR 471 at Box Creek is closed to through traffic while a new bridge is constructed. The project is expected to be completed in August 2015.

CHEROKEE COUNTY – Cherokee County Maintenance is performing overlay level up work on FM 13. The roadway is down to one lane with signage and flaggers providing direction through the work zone.

HENDERSON COUNTY
State Highway 31 Repair Project
*Limits: .09 miles west of FM 317 eastward to .34 miles west of FM 773
*Contractor: Big Creek Construction, Ltd., of Hewitt
*Cost: $3.6 million
Work is underway on this project that calls for milling the existing surface and placing a new overlay on the roadway. It should be completed in three months. Motorists should expect daytime lane closures throughout the duration project.

U.S. Highway 175 Widening Project
*Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
*Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
*Cost: $39.2 million
The project will expand U.S. 175 from two lanes to a four-lane divided roadway with a depressed median. Construction of this Phase I project started April 6, 2015 and should be completed in November 2018.

Farm Road 317 Widening Project
*Limits: From FM 314 to FM 607
*Contractor: Big Creek Construction, Ltd., of Hewitt
Big Creek Construction is conducting cleanup activities and final installations on this job. The project is widening FM 317 from FM 314 to FM 607. Expect lane closures.

Off-System Bridge Replacement Project
*Limits: Cardinal Drive at Little Duncan Creek in Murchison
*Contractor: Hartbeat Construction of Tyler
*Cost: $314,919.44
Cardinal Drive is closed to through traffic while a new bridge is constructed. The project is expected to be completed in August 2015.

RUSK COUNTY – Henderson Maintenance is conducting base and edge repairs on Farm Road 839 from U.S. Highway 79 to Farm Road 1798 as well as base repairs on Farm Road 225 from Farm Road 1798 to U.S. Highway 84. Crews will also be fixing base failures on Farm Road 2658 from State Highway 43 to Farm Road 1251. Expect lane closures at all locations with traffic reduced to one lane.

Detours continue on Farm Road 782, which is closed to through traffic near the north intersection of Farm Road 1716, as the contractor prepares to replace the culvert washed out during recent rain events. Traffic is being redirected to Farm Road 1797 and Farm Road 1716. This job will be completed in about a month.

TxDOT contractor, Striping Technology, Inc., will have a crew adding striping on Farm Road 13, U.S. Highway 79 and State Highway 149 in Rusk County as part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

U.S. Highway 259 Resurfacing Project
*Limits: From FM 315 in Mt. Enterprise north to CR 485 about 3 miles north of the FM 1798 overpass
*Contractor: Madden Contracting Company, LLC
*Cost: $4,309,817.27
The contractor is applying a seal coat on the northbound lanes of US 259 from FM 1798 to SH 315 this week. The project is expected to take approximately two months to complete. Expect lane closures.

State Highway 64 Widening Project
*Limits: 0.173 miles west of BU 64E (N. Marshall St.) east to 0.2 miles west of U.S. 79 (Traffic Star)
*Contractor: Lonestar Equipment Company, Inc.
*Cost: $2.1 million
Motorists should expect periodic delays on this SH 64 construction project in Henderson as the contractor works to widen the roadway. Construction of the retaining wall continues with no impact to traffic at this time. The traffic signal at N. Marshall St. has been removed and Stop Signs installed. The signal at Mill Street will remain but will be upgraded. Use caution through this work zone.

The project started in August 2013 and consists of widening the existing two-lane roadway and constructing a four-lane facility along with a continuous Left Turn Lane with the majority of work being performed outside the existing travel lanes. It is expected to be completed in late summer 2015.

VAN ZANDT COUNTY – Canton Maintenance is placing an overlay on State Highway 110 north of Van from Farm Road 1805 to Farm Road 1255. Expect lanes closures during this job which could take up to two weeks to complete.

TxDOT contractor, Striping Technology, Inc., will have a crew adding striping on these roads in Van Zandt County as part of the district-wide safety project to add centerline rumble strips: State Highway 19, Farm Road 1255, Farm Road 2909, Farm Road 1504, Farm Road 751 and Farm Road 47. Expect lane closures.

VAN ZANDT COUNTY
State Highway 64 Widening Project
*Limits: From FM 858 near Ben Wheeler to FM 314
*Contractor: A.L. Helmcamp, Inc., of Buffalo
*Cost: $7.4 million
Work started in December 2012 on this widening project to add shoulders and passing lanes. The project is expected to be completed in August 2015 but construction is behind due to excessive rain in the spring.

Off-System Bridge Replacement Projects

*Locations:
*County Road (CR) 2702 at Lacy Fork Tributary
*County Road (CR) 2129 at Flat Creek
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $1.02 million
Both roads are open for travel as the contractor conducts final oversight activities.

State Highway 198 Widening Project
*Limits: from SH 243 in Canton southwest to 0.4 miles northeast of FM 316 near Phalba
*Contractor: Big Creek Construction, Ltd., of Waco
*Cost: $5 million
Culvert work continues on this widening project. Expect lane closures.

Farm Road 314 Widening Project
*Limits: from I-20 to the Van Zandt/Henderson County line
*Contractor: A.L. Helmcamp, Inc., of Buffalo
*Cost: $11.9 million
The contractor is finishing rehabilitation work, including dressing up the slopes and placing sod south of Edom. Work also being performed north of FM 279 for one mile. Expect lane closures.

Interstate Highway 20 Project
*Limits: From 1.6 miles east of FM 16 to 2.9 miles east of FM 314
*Contractor: APAC-Texas, Inc.
*Cost: $2.4 million
The contractor is conducting work on the pavement edges on the main lanes and ramps. Expect daily lane closures of one entrance or exit ramp per day. Due to traffic impacts no work is planned for Friday’s.

WOOD COUNTY – Mineola Maintenance continue maintenance work on Loop 564. Expect lane closures.

TxDOT contractor, Striping Technology, Inc., will have a crew adding striping on Farm Road 515, Farm Road 2869 and State Highway 154 in Wood County as part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

Wood County construction project update:
State Highway 37 Roadway Repair
*Limits: from FM 2088 in Quitman to 0.4 miles south of FM 515 in Winnsboro
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $7.7 million
The contractor continues to place the final surface on the length of this project from just south of FM 313 in Winnsboro southward toward FM 2088. Expect lane closures.