Posted/updated on: December 8, 2015 at 2:05 am
Print Friendly, PDF & Email


TxDOT-signTYLER – Here’s a look at work planned in the district during the Week of December 7. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.

ALERT: The westbound lanes of SH 31 remain closed between Malakoff and Trinidad in
Henderson County due to flooding caused by Cedar Creek. All traffic has been moved to the eastbound travel lanes which will continue to carry two-way traffic until the water recedes. That is expected to happen early this week. Motorists should slow down and use caution when traveling through this area until the traffic flow returns to normal.

Contractor crews with CDM Holdings continue to place final striping and buttons on roadways across Smith, Van Zandt, and Henderson counties to finalize districtwide seal coat operations. Expect lane closures in these work zones.

SMITH COUNTY – Tyler Maintenance plans to conduct milling work on northbound U.S. Highway 271 at several locations between the intersections of Interstate Highway 20 (Monday) and Farm Road 16 (throughout the week). The work requires lane closures. Look for arrow boards and other traffic safety devices to help guide you through the work zone. Another crew will be performing ditch maintenance on various farm-to-market roadways around the county. Expect lane closures with flaggers providing traffic control.

TxDOT contractor, Striping Technology, Inc., crews to add striping on FM 346 as part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

Smith County construction projects updates:
Farm Road 1253 Widening Project
*Limits: From County Road 462 south, 1.3 miles north of FM 857 south to FM 1805; FM 1804 from Wood County line to US 69; FM 2015 from CR 313 to FM 16
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $7.5 million
This contract contains three project locations, including the widening, sealing and resurfacing of FM 1253. Currently, drainage work continues on FM 1253 from County Road 462 S, 1.3 miles north of FM 857 southward to FM 1805. No closures expected on FM 1253. Crews working on FM 1804 plan to install driveway culverts which could require closures with flaggers assisting. Current work on FM 2015 does not require lane closures.

Loop 323 West Widening
*Limits: Tyler’s West Loop and SH 31
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $12 million
Temporary detours remain in place as work on the retaining walls, drainage and the new bridge continues. No left turns from Loop 323 onto Bellwood East. Motorists should use caution when traveling through this work zone as crews and heavy equipment are working close to the travel lanes. Expect lane closures. Motorists are encouraged to take alternate routes to avoid delays.

The project includes widening Loop 323 from SH 31 to Shaw Street. The speed limit on Loop 323 in the work zone has been reduced to 45 mph from SH 64 to Shaw Street.
Construction is in full swing with an expected completion date in early 2016.

Loop 323 Northeast Project
*Limits: From American Legion Road (@ the Loop 323 Extension to US 271) south to Commerce St.
*Contractor: Reynolds and Kay, LTD.
*Cost: $3.4 million
Work continues to place mow strips and final striping on this portion of Loop 323. The project includes culvert extensions, base repair, level-up and placing an overlay. Expect daily shoulder closures. Completion expected later this winter.

State Highway 31E Widening Project
*Limits: From FM 757 to FM 2012
*Contractor: Reynolds & Kay, LTD
*Cost: $7.8 million
No work is planned on this project. When work resumes, expect shoulder closures as excavation and embankment work continue on the north side of this project designed to add passing lanes for multiple sections of roadway in both the eastbound and westbound directions. Once the widening is complete, a seal coat and final surface will be applied. A daily construction speed limit of 60 mph is in place when work is being performed on this 18-month job.

State Highway 31E Widening Project
*Limits: From FM 850 to FM 757
*Contractor: East Texas Bridge, Inc.
*Cost: $3.4 million
No work planned for this project which is in the final inspection phase. This project to widen SH 31 east of Tyler includes adding passing lanes for multiple sections of the roadway in both directions. The new passing lanes are open to traffic. Expect shoulder closures.

State Highway 64
*Limits: from Chapel Hill to Arp
*Contractor: Drewery Construction of Nacogdoches
*Cost: $3.9 million
Expect lane closures as crews lay a new hot mix surface on the roadway. This job is adding passing lanes between FM 2607 and Arp. Motorists are urged to use extra caution when traveling through this work zone.

GREGG COUNTY – Longview crews plan to continue asphalt mill and inlay work on U.S. Highway 271 through Gladewater. Expect lane closures in NB and SB lanes.

Gregg County construction projects updates:
Interstate Highway20 Total Maintenance Contract
*Limits: Gregg, Smith and Van Zandt counties
*Contractor: Fireman Excavating
The contractor has moved the work to the eastbound and westbound mainlanes in Smith County. Expect lane closures and delays during this work.

State Highway 31 Landscape Project
*Limits: 0.3 miles north of FM 2205 (Grace Creek) to 0.2 miles south of U.S. 80 (Cotton) in Longview
*Contractor: South Texas Illuminations, LLC
*Cost: $281,249.70
Final work continues for this project which comes as a result of the city winning one of 10 Governor’s Community Achievement Awards presented by Keep Texas Beautiful in partnership with TxDOT which allocates $2,000,000 a year as landscape incentives to competing communities based on population and efforts in litter prevention and cleanup, public awareness, beautification and property improvement, solid waste management, illegal dumping and enforcement, and education. No traffic impacts.

Farm Road 2275 George Richey Extension (Segments II & III)
*Limits: McCann Road to US 259
*Contractor: East Texas Bridge, Inc.
*Cost: $12.8 million
This project is constructing a new roadway from McCann Road to US 259. Clearing between Judson and Airline roads continues with excavation, embankment, bridge construction, subgrade treatment, storm drain and other work between McCann and
Judson roads. The contractor recently began paving operations. While this is a new location project that generally doesn’t impact traffic motorists should plan to take other routes to get around Airline Road which is closed through March 2016.

Farm Road 449
*Limits: US 259 to FM 2751
*Contractor: Madden Contracting Company, LLC
No work planned this week on this project to widen the road and add shoulders.

Loop 281 at Farm Road 2087 Overpass
*Limits: SH 31 to approximately one mile south of SH 31
*Contractor: Longview Bridge and Road, Ltd., of Longview.
*Cost: $13.2 million
This project to build a new overpass is in Phase III of construction with traffic moved off the existing loop onto the detours. Work on the bridge approaches is ongoing. Expect delays during the peak evening hours. Caution advised in detour areas.

State Highway 42
*Limits: From SH 31 north to I-20
*Contractor: Reynolds & Kay, Ltd.
*Cost: $3.7 million
The contractor plans to complete cleanup activities as well as sodding and edge embankment work. Some work requires closures. The project is constructing a left turn lane at Hillcrest Road along with storm drain and curb and gutter. Project completion expected soon. Expect lane closures with flaggers directing traffic.

Interstate Highway20 PFC Project
*Limits: SH 31E to the Harrison County line
*Contractor: Madden Contracting Company, LLC
*Cost: $5,584,277
Motorists should expect daytime delays as the contractor applies striping to the I-20 mainlanes. Asphalt will also be placed on the on ramps and frontage roads at Estes Parkway/SH 322 and Eastman Road/US 259 requiring intermittent closures. Mainlane closures necessary as well for asphalt tie-ins. Alternate routes encouraged if possible. The project consists of applying a porous friction course (PFC) surface overlay, shoulder texturing, and pavement markings as well as work on the I-20 on ramps. Porous friction courses (PFC) consist of placing hot mix asphalt mixtures at the surface of a pavement structure in a thin layer to produce benefits for the traveling public such as safety, economy and the environment.

Landscaping Projects
*Limits: Intersection of SH 31 at SH 42
*Limits: Intersections of I-20 at Estes Parkway; and I-20 at Eastman Road
*Contractor: South Texas Illuminations, LLC
*Cost: $400,000
This is a landscaping project to enhance various intersections throughout Gregg and Rusk counties. Crews are working at the intersections of SH 42 and SH 31, and I-20, Estes Pkwy and Eastman Road. The majority of the work is outside the travel lane in the median and should have little impact on traffic. The travelling public should be cautious of construction vehicles entering and leaving the project sites.

ANDERSON COUNTY – Palestine crews plan to conduct hot mix level up work on Farm Road 861 in Elkhart before moving to State Highway 294 west of Elkhart. Expect lane closures with flaggers directing traffic.

Anderson County construction projects updates:
U.S. Highway 79 New Lane Construction
*Limits: 1.6 miles southwest of Loop 256 in Palestine south to .4 mile southwest of FM 645
*Contractor: Longview Bridge and Road, Ltd., of Longview.
*Cost: $42,740,365.19
The project continues to progress with the contractor performing flex base on the south end of the job. Work in the southbound lanes includes cleanup concrete work and other activities in the curb and gutter section. Sanderson Blvd. remains closed for the next few weeks with traffic detoured to Florence Street. Expect lane closures.

State Highway 19 Widening in Anderson County
*Limits: 3.6 miles north of FM 837 (Henderson Co. line) south to .4 mile north of FM 321 at Montalba
*Contractor: Big Creek Construction of Hewitt
*Cost: $12,487,715.87
Work is ongoing to widen SH 19 in this area. Lane closures and delays are to be expected as flex base and cement treat operations progress. Flaggers and a pilot car are providing traffic control.

Off-System Bridge Replacement Project
*Limits: County Road (CR) 471 at Box Creek and County Road (CR) 4801 at Indian Creek
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $817,412.15
CR 471 at Box Creek is closed to through traffic as a new bridge is built. Completion is set for January. CR 4801 at Indian Creek is also closed to through traffic with right-of-way work underway in preparation for building a new bridge.

CHEROKEE COUNTY – Jacksonville and Rusk crews plan to conduct winter preparation
activities and perform base repairs on roadways throughout the county. Expect lane closures with flaggers directing traffic.

TxDOT contractor, Striping Technology, Inc., crews to add striping on Farm Road 347 as part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

Farm Road 22 and Farm Road 23 Widening Project
*Limits: From US 69 south of Jacksonville going SW to 1.5 miles west of FM 768 (Gallatin area); FM 23 from FM 343 to FM 1857
*Contractor: Madden Contracting Company, LLC
*Cost: $8.5 million
No work is planned for either roadway at this time. This is a safety project designed to widen the roadway from 20′ to 24′ along a 4.2 mile section.

U.S. Highway 69 Widening and Resurfacing
*Limits: From Loop 456 in Jacksonville going south to just north of Loop 62 in Rusk
*Contractor: Madden Contracting Company, LLC
*Cost: $11.5 million
The contractor continues work in the median on this project to add 2′ edge treatment and resurfacing the roadway. No planned lane closures.

U.S. Highway 69 Widening and Resurfacing
*Limits: From 0.028 mile south of FM 343 in Rusk southward to just north of SH 21 in Alto
*Contractor: Madden Contracting Company, LLC
*Cost: $9.7 million
No work is currently scheduled for this project.

HENDERSON COUNTY – Athens crews this week plan to conduct edge repair work on Farm Road 607 between State Highway 31 and Farm Road 317 in the Leagueville area, and address maintenance issues such as potholes and debris. This work will be followed by edge repairs on Farm Road 317 between Farm Road 314 and Farm Road 315. Maintenance work is also planned around Loop 7. Expect lane closures with flaggers providing traffic control.

TxDOT contractor, Striping Technology, Inc., crews to add striping on Farm Road 2709 as
part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

Henderson County construction projects updates:
State Highway 31 Repair Project
*Limits: .09 miles west of FM 317 eastward to .34 miles west of FM 773
*Contractor: Big Creek Construction, Ltd., of Hewitt
*Cost: $3.6 million
The contractor is currently placing striping on this roadway and anticipates guardrail work to start soon. The project consists of milling the existing surface and placing a new overlay on the roadway. Expect lane closures on this job which is expected to be completed by the end of this month.

U.S. Highway 175 Widening Project (Phase I)
*Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
*Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
*Cost: $39.2 million
The project expands US 175 from two lanes to a four-lane divided with a depressed median. A traffic switch now has eastbound motorists driving on the new detour. Drivers should expect one lane carrying two-way traffic throughout the project limits as well as occasional day time lane closures. Drivers on adjacent county roads and FM 804 should anticipate a change in traffic flow due to the detour now requiring two-way traffic on US 175. Dirt and drainage work around Loop 60E in Larue to near Baxter is ongoing. The speed limit in the construction zone has been set at 55 mph so slow down because traffic fines double when workers are present. Phase I construction started April 6, 2015 and has an anticipated completion date in November 2018.

U.S. Highway 175 Widening Project (Phase II)
*Limits: 1.1 miles east of Loop 60B to 0.85 mile east of FM 315
*Contractor: Sundt Construction, Inc., of San Antonio
*Cost: $37.8 million
Construction is underway on this Phase II project to expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 3.4 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase will be built on new location around the south side of Poynor. This like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction. It is a two-year project.

Farm Road 315/Farm Road 1616 Widening Project
*Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
*Contractor: Big Creek Construction, LTD, of Hewitt, Texas
*Cost: $3.07 million
Work is underway to add shoulders on FM 315. Drivers should anticipate two-way traffic throughout the project limits with daily lane closures. Completion expected in summer 2016.

Farm Road 316 Widening Project
*Limits: From FM 1256 south to FM 3080
*Contractor: Big Creek Construction, Ltd., of Hewitt
No work is planned this week on this widening project.

Off-System Bridge Replacement Project
*Limits: Cardinal Drive at Little Duncan Creek in Murchison
*Contractor: Hartbeat Construction of Tyler
*Cost: $314,919.44
Cardinal Drive is closed to through traffic as a new bridge is built. Completion set for January.

RUSK COUNTY – Henderson crews plan to continue edge repairs on Farm Road 839 between Farm Road 1662 and U.S. Highway 84 for the next couple of weeks. Expect lanes closures with traffic control provided by flaggers and a pilot car.

Rusk County construction projects updates:
Farm Road 3135
*Limits: County Road 222 to County Road 262
*Contractor: Madden Contracting Company, LLC
This project consists of widening the road and adding shoulders. Contractor will be installing safety end treatments on driveways and extending cross culverts. Asphalt is also being applied on mainlanes and edge widening. Expect lane closures and two-way traffic control with flaggers and a pilot vehicle. Expect delays. Slow down and use caution.

Farm Road 95
*Limits: FM 1798 to SH 315
*Contractor: Madden Contracting Company, LLC
This project consists of widening the road and adding shoulders. Contractor will be installing safety end treatments on driveways and extending cross culverts. Traffic can expect some delays. Motorists are reminded to use caution in this and all work zones.

U.S. Highway 79 Repair Project Night Operations
*Limits: From FM 225 going north to the Traffic Star (intersection of US 79/SH 64/SH 43/US 259)
*Contractor: Madden Contracting Company
*Cost: $5.2 million
Daytime work continues with striping of the mainlanes during the day. Lane closures and delays can be expected as work is conducted Monday through Friday. Watch for flaggers providing traffic control. The resurfacing project is expected to be completed this winter providing motorists a smoother, safer ride.

State Highway 64 Widening Project
*Limits: 0.173 miles west of BU 64E (N. Marshall St.) east to 0.2 miles west of U.S. 79 (Traffic Star)
*Contractor: Lonestar Equipment Company, Inc.
*Cost: $2.1 million
The contractor plans to implement mill and inlay asphalt operations in the mainlanes. Expect lane closures on this job to widen SH 64 through Henderson.

The project started in August 2013 and consists of widening the existing two-lane roadway and constructing a four-lane facility along with a continuous Left Turn Lane with the majority of work being performed outside the existing travel lanes.

VAN ZANDT COUNTY – Canton crews continue to address maintenance issues around the county including ditch work, patching potholes, mailbox requests, and other
activities.

TxDOT contractor, Striping Technology, Inc., crews to add striping on Farm Road 47 and Farm Road 2909 as part of the district-wide safety project to add centerline rumble strips.
Expect lane closures.

Van Zandt County construction projects updates:
State Highway 64 Widening Project
*Limits: From FM 858 near Ben Wheeler to FM 314
*Contractor: A.L. Helmcamp, Inc., of Buffalo
*Cost: $7.4 million
The new passing lanes are open to traffic as crews continue to apply the final hot mix surface to the roadway. This work is expected to be completed later this month, weather permitting, so motorists should be prepared for daily lane closures. This project is expected to improve safety and mobility on SH 64.

State Highway 198 Widening Project
*Limits: from SH 243 in Canton southwest to 0.4 miles northeast of FM 316 near Phalba
*Contractor: Big Creek Construction, Ltd., of Waco
*Cost: $5 million
Work continues to extend the structures on the east side of the roadway. Expect lane closures.

Farm Road 314 Widening Project
*Limits: from I-20 to the Van Zandt/Henderson County line
*Contractor: A.L. Helmcamp, Inc., of Buffalo
*Cost: $11.9 million
Erosion control activities continue south of Edom. No lane closures planned.

Purtis Creek State Park Road Improvements Project
*Limits: Within Purtis Creek State Park to just off FM 316
*Contractor: Construction Companies Group, LLC
*Cost: $90,549.00
Cleanup work continues on this project to upgrade Park Road which runs .573 miles inside the park. It should be completed soon. No lane closures planned.

WOOD COUNTY – Mineola crews plan to address routine maintenance issues around the
county including shoulder work on Loop 564; ditch work on Farm Road 779 near State Highway 37; and level up and edge repairs on Farm Road 515 west of Farm Road 2225. Expect lane closures at all locations with flaggers providing traffic control.

TxDOT contractor, Striping Technology, Inc., crews to add striping on Farm Road 515, Farm Road 2869, and State Highway 154 as part of the district-wide safety project to add centerline rumble strips. Expect lane closures.

Wood County construction projects updates:
State Highway 37 Roadway Repair
*Limits: from FM 2088 in Quitman to 0.4 miles south of FM 515 in Winnsboro
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $7.7 million
Cleanup work continues from 0.4 miles south of FM 515 in Winnsboro southward to FM 2088. No lane closures expected.

Farm Road 2869 Project
*Limits: From FM 852, south of Winnsboro going south to FM 2088
*Contractor: Longview Bridge and Road, Ltd., of Longview
Surface work on driveways and other activities continue in the NB and SB lanes within the project limits. Expect lane closures.