TxDOT’s Weekly Roadwork Update

Posted/updated on: July 26, 2016 at 11:31 am
Print Friendly, PDF & Email


TxDotTYLER – Here’s a look at work planned in TxDOT’s Tyler District during the Week of July 25. These schedules are subject to change due to weather conditions, equipment failure, or other unforeseen issues.

In Tyler, the US 271 closure has been rescheduled for July 28 – 31. US 271 will be closed from Oakwood Street to Spur 147 for pavement repairs. Motorists will have to use temporary detours to get around the closure. Message boards are in place to alert traffic to this upcoming change along the project limits. Additional project information is available in the Smith County section of this news release.

In Cherokee County, County Road (CR) 2303 at One Eye Creek south of Rusk is now closed to traffic for a bridge replacement project. The contractor plans to close CR 1707 at One Arm Creek west of Rusk on Wednesday, July 27 to replace the bridge. Both roads will be closed for several months requiring motorists to use other routes to reach their destinations. More information is available in the Cherokee County section of this release.

SMITH COUNTY – Tyler Maintenance plans to conduct shoulder repairs on FM 2015 between FM 16 and FM 14. Expect lane closures with flaggers providing traffic control. A second crew will conduct ditch maintenance on roads around the county. This work will have minimal impact on traffic but lane closures are possible.

Smith County construction projects updates:

Loop 323 West Widening at UPRR Underpass

β€’ Limits: Tyler’s West Loop and SH 31

β€’ Contractor: Longview Bridge and Road, Ltd., of Longview

β€’ Cost: $12 million

β€’ Anticipated Completion Date: Winter 2016

The contractor continues work on the new railroad bridge and to place hot mix in the northbound lanes. Sidewalk work continues along work on the northbound lanes and Bellwood Road West. A temporary detour is in place. The project includes widening Loop 323 from SH 31 to Shaw Street. The speed limit on Loop 323 in the work zone has been reduced to 45 mph from SH 64 to Shaw Street.

SH 31E Widening Project

β€’ Limits: From FM 757 to FM 2012

β€’ Contractor: Reynolds & Kay, LTD

β€’ Cost: $7.8 million

β€’ Anticipated Completion Date: Summer 2017

Work continues on the eastbound passing lanes. Expect lane closures on this project designed to add passing lanes for multiple sections of roadway in both the eastbound and westbound directions. Once the widening is complete, a seal coat and final surface will be applied. A daily construction speed limit of 60 mph is in place when work is being performed.

SH 64

β€’ Limits: from Chapel Hill to Arp

β€’ Contractor: Drewery Construction of Nacogdoches

β€’ Cost: $3.9 million

β€’ Anticipated Completion Date: Summer 2016

Drainage work continues on this project to add passing lanes between FM 2607 and Arp. Expect lane closures.

FM 1253 Widening Project

Limits: From County Road 462 south, 1.3 miles north of FM 857 south to FM 1805; FM 1804 from Wood County line to US 69; FM 2015 from CR 313 to FM 16
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $7.5 million
Anticipated Completion Date: Fall 2016

No work or lane closures planned for FM 1253 or FM 1804. Drainage work is ongoing on FM 2015 as well as pavement repairs. Expect lane closures. This contract consists of widening, sealing and resurfacing all three roadways.

Spur 164 Bridge Project

Limits: From just south of the railroad tracks at Indian Creek in Tyler
Contractor: L.C. Jordan and Sons of Lufkin
Cost: $324,059.81
Anticipated Completion Date: Summer 2016

The bridge has been repaired and the roadway is open to traffic with minor cleanup activities ongoing.

Spur 248 Widening Project

Limits: From 1.75 miles west of FM 848/Old Omen Road going east to SH 64 southeast of Tyler
Contractor: Lonestar Equipment Company, Inc.
Cost: $8.6 million
Anticipated Completion Date: Summer 2018

Culvert work continues in preparation of moving traffic. Expect lane closures. The speed limit has been reduced to 55 mph during construction. This project will widen Spur 248 from two lanes to a four-lane divided roadway with flush median.

County Road Bridge Replacement Projects

Β· Limits: CR 4129 at Mud Creek near Lindale; CR 3104 at Prairie Creek north of FM 1252 near Winona; and CR 2138 at Blackhawk Creek south of Whitehouse

Β· Contractor: Pierce Construction

Β· Cost: $947,000.00

Β· Anticipated Completion Date: Summer 2017

County Roads (CR) 3104 and CR 4129 are currently closed as work to build new bridges and approaches progresses. Each road will be closed for about six months.

US 271 Repairs and Resurfacing Project

Limits: From FM 2015 southward to Oakwood Street/Spur 147 in Tyler
Contractor: Reynolds & Kay
Cost: $4.3 million
Anticipated Completion Date: Fall 2016

Pavement repairs are underway north of Spur 147. Expect lane closures. Additionally, US 271 from Oakwood Street to Spur 147 is tentatively scheduled to close July 28-31 for pavement repairs on this 4.5-mile project to repair and resurface the roadway. Detours will be in place to guide traffic through the work zone.

I-20 Resurfacing Project

Limits: Eastbound lanes from FM 14 eastward to US 271
Contractor: Clark Construction
Cost: $2 million
Anticipated Completion Date: Fall 2016

Work is underway with the contractor placing the PFC surface starting Monday on this project to resurface a 4.8-mile stretch of I-20. Expect lane closures.

GREGG COUNTY – Longview Maintenance plans to perform mill and hot mix inlay work on FM 3272 between US 80 and FM 2275. Expect lane closures with the travel lanes reduced and flaggers directing traffic.

Gregg County construction projects updates:

FM 2275 George Richey Extension (Segment I)

Limits: McCann Road west to SH 300 (Gilmer Road)
Contractor: East Texas Bridge, Inc.
Cost: $12.4 million
Anticipated Completion Date: Fall 2017

McCann Road remains closed as the contractor builds tie-ins to the new intersection. The closure runs from just north of Graystone Road to about 200 feet north of the new road. No through traffic is allowed at this location but northbound and southbound traffic does have access on McCann Road north of the intersection. Residents can travel southward from FM 1844 to the new George Richey Road but cannot cross. Motorists are encouraged to take alternate routes to avoid delays. Meanwhile, the contractor is hauling embankment as utility relocation and clearing of right of way activities continue on this new roadway construction to connect Gilmer and McCann roads.

This Segment I project includes constructing two bridges and a four-lane roadway with center left turn lanes from McCann Road to SH 300/Gilmer Road. Excavation, embankment, bridge construction, subgrade treatment, storm drains, hot mix asphalt, curb and gutter and sidewalk are all part of the new construction.

FM 2275 George Richey Extension (Segments II & III)

β€’ Limits: McCann Road to US 259

β€’ Contractor: East Texas Bridge, Inc.

β€’ Cost: $12.8 million

β€’ Anticipated Completion Date: Late Summer 2016

The outside southbound lane of Judson Road remains closed as the contractor makes tie-ins to the new FM 2275. Paving operations continue along with construction of curb and gutter, and sidewalk, between US 259 and McCann Road. Between Judson and US 259, construction continues with hot mix asphalt, curb and gutter, sidewalk and storm drain work. This project is constructing a new roadway from McCann Road to US 259. Motorists must use other routes to get around Airline Road which remains closed through July 2016.

FM 449

Limits: US 259 to FM 2751
Contractor: Madden Contracting Company, LLC
Cost: $607,133.00
Anticipated Completion Date: Late Summer 2016

No work is planned on this project where the contractor is widening the road two feet on each side and applying an overlay.

Loop 281 at FM 2087 Overpass

β€’ Limits: SH 31 to approximately one mile south of SH 31

β€’ Contractor: Longview Bridge and Road, Ltd., of Longview.

β€’ Cost: $13.2 million

β€’ Anticipated Completion Date: Late Fall 2016

The contractor continues construction on the concrete paving at the south end of the bridge and at the new SH 31 intersection on this project that is building a new overpass over the railroad crossing. Expect delays during the peak evening hours.

ANDERSON COUNTY – Palestine Maintenance plans to conduct overlay work on US 287 the first of the week before moving to US 79 to conduct base repairs between the Anderson County line and SH 294. Expect the roadway to be reduced to one lane with flaggers providing traffic control.

Anderson County construction projects updates:

US 79 New Lane Construction Project

β€’ Limits: 1.6 miles southwest of Loop 256 in Palestine south to the Trinity River

β€’ Contractor: Longview Bridge and Road, Ltd., of Longview.

β€’ Cost: $42.7 million

β€’ Anticipated Completion Date: End of 2016

On this project, work currently centers on the area from CR 2205 to just south of FM 645. The contractor is working on detours in the area of FM 645 at Tucker. This project expands a 5.3 mile section of US 79 from two lanes to a four-lane divided highway with a continuous left turn lane and a depressed median. Work started in November 2012.

SH 19 Widening

Limits: 3.6 miles north of FM 837 (Henderson Co. line) south to .4 mile north of FM 321 at Montalba

β€’ Contractor: Big Creek Construction of Hewitt

β€’ Cost: $12.5 million

β€’ Anticipated Completion Date: Summer 2017

Utility work continues along the right of way where this roadway is being widened.

Off-System Bridge Replacement Project

Limits: County Road (CR) 471 at Box Creek; CR 4801 at Indian Creek; CR 1231 at Stills Creek
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $817,412.15
Anticipated Completion Date: Fall 2016

Work is progressing on the bridge replacement project on County Road 1231 at Stills Creek. The roadway is closed to traffic with detours in place. The new bridges at Box Creek and Indian Creek are open to traffic with the contractor continuing closeout activities.

CHEROKEE COUNTY – Jacksonville and Rusk crews plan to perform sealing operations on FM 2493 through Wednesday. Expect lane closures with flaggers providing traffic control.

Cherokee County construction projects updates:

US 69 Widening and Resurfacing

Limits: From Loop 456 in Jacksonville going south to just north of Loop 62 in Rusk
Contractor: Madden Contracting Company, LLC
Cost: $11 million
Anticipated Completion Date: Summer 2016

The contractor will start placing the PFC surface on this project to widen US 69 by adding 2’ edge treatment and resurface the road. Expect lane closures.

US 69 Widening and Resurfacing

Limits: From 0.028 mile south of FM 343 in Rusk southward to just north of SH 21 in Alto
Contractor: Madden Contracting Company, LLC
Cost: $9.3 million
Anticipated Completion Date: Fall 2016

No work is scheduled on this project to widen and resurface US 69.

US 69 Widening and Resurfacing

Limits: From .37 miles north of FM 344 to .02 miles north of FM 347
Contractor: Madden Contracting Company, LLC
Cost: $5.6 million
Anticipated Completion Date: Summer 2016

The contractor plans to begin final cleanup on this project to widen and resurface this portion of US 69.

US 79 Repairs and Resurfacing Project

Limits: From SH 204 to Mud Creek
Contractor: Reynolds & Kay
Cost: $5.7 million
Anticipated Completion Date: Summer 2017

The contractor is removing the pavement to allow for reworking the subgrade. Traffic has been moved to the new temporary detour. Motorists can expect lane closures for the remainder of the project and are encouraged to avoid this location when possible. The roadway is being repaired and resurfaced.

FM 22 and FM 23 Widening Project

Limits: From US 69 south of Jacksonville going SW to 1.5 miles west of FM 768 (Gallatin area); FM 23 from FM 343 to FM 1857
Contractor: Madden Contracting Company, LLC
Cost: $8.5 million
Anticipated Completion Date: Fall 2016

The contractor resumes hot mix applications for driveways on FM 22. Expect lane closures. No work is planned for FM 23. These are safety projects designed to widen the roadways from 20’ to 24’ along a 4.2-mile section.

County Road Bridge Replacement Projects

Limits: CR 1707 at One Arm Creek west of Rusk between FM 347 and FM 2138 and CR 2303 at One Eye Creek south of Rusk between FM 23 and FM 752
Contractor: Stateline Construction
Cost: $699,993.90
Anticipated Completion Date: Winter 2016

CR 2303 is closed and work is underway to remove the existing bridge. CR 1707 is scheduled to close on July 27, 2016. Both roads will be closed for about six months.

HENDERSON COUNTY – Athens Maintenance plans to conduct base repairs on FM 316 and address routine maintenance on roads around the county. Expect lane closures with flaggers directing traffic.

Henderson County construction projects updates:

FM 317 Repair Project

Limits: At Athens Fish and Game Lake Dam
Contractor: Fritcher Construction
Cost: $446,216.00
Anticipated Completion Date: Late Summer 2016

Repair work is progressing on schedule for this roadway/bridge in an effort to get it open to traffic again. The road closed in March 2015 due to a flood-related washout about three miles east of SH 31. Repairs are expected to be completed later this summer, weather permitting. The plans for the permanent repairs have been coordinated with the Corp of Engineers and the Texas Commission on Environmental Quality (TCEQ).

US 175 Widening Project (Phase I)

Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
Cost: $39.2 million
Anticipated Completion Date: November 2018

The eastern portion of Loop 60 is closed through the summer for construction of the new westbound mainlanes on this project that expands US 175 from two lanes to a four-lane divided with a depressed median. Drivers should expect one lane carrying two-way traffic throughout the project limits as well as occasional day time lane closures. Drivers on adjacent county roads and FM 804 should anticipate a change in traffic flow due to the detour now requiring two-way traffic on US 175. Dirt and drainage work around Loop 60E in Larue to near Baxter is ongoing. The speed limit in the construction zone has been set at 55 mph so slow down because traffic fines double when workers are present. Phase I construction started April 6, 2015.

US 175 Widening Project (Phase II)

Limits: 1.1 miles east of Loop 60B at LaRue to 0.85 mile east of FM 315 at Poynor
Contractor: Sundt Construction, Inc., of San Antonio
Cost: $37.8 million
Anticipated Completion Date: Late Summer 2017

The contractor continues dirt work around FM 315 south of Poynor as well as drainage work throughout the project. As part of the new highway construction, a short stretch of CR 4401 has been permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 remains open with access from CR 4345/Camp Road.

This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.

US 175 Widening Project (Phase III)

Limits: 0.85 miles east of FM 315 in Poynor, southeast to .5 miles NW of SH 155 at Frankston
Contractor: A.L. Helmcamp, Inc.
Cost: $27.6 million
Anticipated Completion Date: Spring 2019

On Monday, the contractor expects to begin clearing right of way near the Poynor city limits. Additionally, earthwork operations continue from the city limits to County Road (CR) 303 as does the installation of drainage culverts west of CR 303. Expect daily lane closures. This project is expanding US 175 from two lanes to a four-lane divided highway with a depressed median.

FM 315/FM 1616 Widening Project

Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
Contractor: Big Creek Construction, LTD, of Hewitt, Texas
Cost: $3.07 million
Anticipated Completion Date: Late Summer 2016

The construction widening project is ongoing with work to extend the cross structures. One-way traffic can be expected throughout the project limits with daily lane closures. FM 1616 is expected to be completed this summer. Final work is being performed on FM 315.

SH 31 Bridge Painting Project – Westbound at Trinity River/Eastbound at Cedar Creek

Limits: From just east of Cedar Creek to just west of the Trinity River
Contractor: Olympus Painting Contractors Inc., of Clearwater, Florida
Cost: $2.3 million
Anticipated Completion Date: Summer 2016

The next phase of work on this project will occur under the bridges once the ground dries. Work on the bridge decks has been completed on both the westbound Trinity River Bridge and the eastbound Cedar Creek Bridges.

RUSK COUNTY – Henderson Maintenance plans to resume milling operations on SH 64 between Loop 571 and the Smith County line. Base repair work continues on FM 1513 from SH 323 to FM 850. Expect the roads to be reduced to one lane carrying two-way traffic with flaggers and a pilot car conducting traffic control.

Rusk County construction projects updates:

US 259 South Project

Limits: Southbound lanes from 0.4 miles S of US 79 in Henderson south to 0.4 miles N of FM 1798

Contractor: Madden Contracting Company, LLC
Cost: $5.7 million
Anticipated Completion Date: Summer 2016

The contractor is working on miscellaneous cleanup activities this week. The 10.13-mile project includes base repair work, mill and inlay of the asphalt surface, placing a PFC overlay, and upgrading pavement markings.

US 79 South Project

Limits: From Loop 571 in Henderson going southwest for 3.0 miles to FM 839
Contractor: Drewery Construction Co., Inc.
Cost: $6.7 million
Anticipated Completion Date: Summer 2017

The contractor continues widening operations on this portion of US 79. Expect lane closures and delays with one-way traffic control. Flaggers and a pilot car will guide traffic through the work zone. Work continues to place embankment on the widened edges. The posted speed limit has been reduced to 60 mph throughout this work zone and is being enforced by DPS. The project includes widening the existing pavement and adding a center left turn lane resulting in a new asphalt surface when the job is completed.

FM 3135

Limits: 1.9 miles NE of US 79 (W of CR 222) north to 1.7 miles SW of FM 1251 (CR 262)
Contractor: Madden Contracting Company, LLC
Cost: $2 million
Anticipated Completion Date: Late summer 2016

The contractor plans to install permanent signage on the project this week with minimal impact to traffic. The project consists of widening the pavement and installing milled centerline rumble strips on this three-mile section of roadway.

FM 95

Limits: FM 1798 to SH 315
Contractor: Madden Contracting Company, LLC
Cost: $2.5 million
Anticipated Completion Date: Late summer 2016

The contractor plans to conduct culvert work on the project this week. Expect lane closures with flaggers providing traffic control. The project is widening a four-mile section of the road and adding shoulders.

FM 1798 Overlay Project

Limits: From US 259 to FM 225
Contractor: Madden Contracting Company, LLC
Cost: $1.8 million
Anticipated Completion Date: Late summer 2016

The contractor expects to conduct overlay operations and lay driveways this week. Expect lane closures with two-way traffic controlled by flaggers and a pilot car. The project consists of placing an asphalt overlay on the roadway.

SH 43 Overlay Project

Limits: From four miles south of FM 2658 to FM 3231
Contractor: Madden Contracting Company, LLC
Cost: $4.6 million
Anticipated Completion Date: Fall 2016

The contractor is installing metal beam guard fence this week. The project consists of placing an asphalt overlay on the roadway, base repairs, and new metal beam guard fence. The contractor will be patching base failures this week. Expect lane closures with two-way traffic control with flaggers and a pilot car.

VAN ZANDT COUNTY – Canton crews plan to conduct work on various roadways around the county. Some of the work could require lane closures causing brief delays.

Van Zandt County construction projects updates:

SH 64 Widening Project (Notice of Completion)

Limits: From FM 858 near Ben Wheeler to FM 314
Contractor: A.L. Helmcamp, Inc., of Buffalo
Cost: $7.4 million

This job is complete. The newly added passing lanes are open to traffic and the project is expected to be completed soon. The project will improve safety and mobility for traffic on SH 64.

SH 198 Widening Project

Limits: from SH 243 in Canton southwest to 0.4 miles northeast of FM 316 near Phalba
Contractor: Big Creek Construction, Ltd., of Waco
Cost: $5 million
Anticipated Completion Date: Fall 2016

Work continues to extend the cross structures along this roadway as does backfilling of pavement edges on this widening project. Expect lane closures.

FM 316 Widening Project

Limits: From FM 1256 south to FM 3080
Contractor: Big Creek Construction, Ltd., of Hewitt
Cost: $255,474.00
Anticipated Completion Date: Fall 2016

The contractor continues to backfill around structures and pavement edges on this widening project which also includes installing safety end treatments and advance warning signs. Expect lane closures.

FM 314 Widening Project

β€’ Limits: from I-20 to the Van Zandt/Henderson County line

β€’ Contractor: A.L. Helmcamp, Inc., of Buffalo

β€’ Cost: $11.9 million

β€’ Anticipated Completion Date: Summer 2018

Expect lane closures as the contractor continues work to extend structures and install driveway pipe between SH 64 and I-20. The contract also includes rehabbing the road north of SH 64.

FM 279 Resurfacing Project

β€’ Limits: from FM 858 in Ben Wheeler east to FM 314 in Edom

β€’ Contractor: APAC – Texas

β€’ Cost: $2.3 million

β€’ Anticipated Completion Date: Later this summer

Cleanup activities continue on this project as does hot mix mill and inlay operations between Edom and Ben Wheeler. Expect lane closures.

FM 1256

β€’ Limits: from FM 316 eastward to SH 19

β€’ Contractor: Longview Bridge and Road, Ltd.

β€’ Cost: $5.8 million

β€’ Anticipated Completion Date: Fall 2018

Installation of storm water control measures and driveway pipe along with work to extend the structures along the project limits is ongoing. The project is widening almost 8 miles of the roadway. Expect lane closures.

County Roads Bridge Replacement Projects

β€’ Limits: CR 3105 at Crooked Creek, CR 3809 at Negro Creek, CR 4404 at Cream Level Creek, and CR 2908 at Purtis Creek

β€’ Contractor: Stateline Construction, LLC.

β€’ Cost: $1.4 million

β€’ Anticipated Completion Date: Summer 2017

The contractor is currently installing temporary shoring and backfilling for a temporary detour on CR 3809. Once the detour is completed, the existing bridge will be removed and construction of a new one will begin. No lane closures planned.

WOOD COUNTY – Mineola Maintenance plans to conduct base repairs on FM 1647, ditch maintenance on SH 37, and pavement work on US 80 west of Mineola. Expect lane closures with flaggers directing traffic.

I-20 Total Maintenance Contract

Limits: Gregg, Smith and Van Zandt counties
Contractor: Fireman Excavating

Routine maintenance activities are ongoing on I-20 with moving operations throughout the week:

– Debris Removal: Monday and Thursday from the inside lane through all three counties

– Debris Removal: Tuesday and Friday from the outside lane through all three counties

– Tree Removal: In Gregg County on Monday and Tuesday

– Mowing: In Smith County Monday/Tuesday and Van Zandt County the rest of the week

– Striping Activities: Van Zandt County, Monday/Friday; Smith County, Tuesday-Thursday

No lane closures planned but that is subject to change.