Today is Friday March 29, 2024
ktbb logo


TxDot Road Projects

Posted/updated on: December 6, 2016 at 11:47 am
Print Friendly, PDF & Email


TxDOT signTYLER – Here’s a look at work planned in the district during the Week of December 5th. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.

In Tyler, a couple of repair jobs are planned for Loop 323. Monday and Tuesday from 9:00am to 3:00pm., crews will be performing base repair work on the Loop 323 Extension. The work requires lane closures with periodic detours around the extension using US 271.

Elsewhere in Tyler, work to repair a retaining wall in front of Furniture Row starts Monday, December 5, on Loop 323. The work is being conducted in the ditch but could require periodic closures of the outside lane. No major impact to traffic is expected.

Smith County – Tyler Maintenance plans to continue edge work on Farm Road 2710 between Farm Road 14 and Farm Road 16, conduct base repairs on the Loop 323 Extension near US 271, and perform ditch maintenance around the county. Expect lane closures at both locations with flaggers providing traffic control.
Work starts Monday to repair a retaining wall in front of Furniture Row on Loop 323. No major impact to traffic is expected but could occur as work is conducted in the ditch.
Smith County construction projects updates:
Loop 323 West Widening at UPRR Underpass
• Limits: Tyler’s West Loop and SH 31
• Contractor: Longview Bridge and Road, Ltd., of Longview
• Cost: $12 million
• Anticipated Completion Date: Winter 2016
General cleanup and closeout activities continue as this job nears completion. The project includes widening Loop 323 from SH 31 to Shaw Street. The speed limit on Loop 323 in the work zone has been reduced to 45 mph from SH 64 to Shaw Street.
State Highway 31E Widening Project
• Limits: From FM 757 to FM 2012
• Contractor: Reynolds & Kay, LTD
• Cost: $7.8 million
• Anticipated Completion Date: Summer 2017
Work is ongoing on the westbound passing lanes as the contractor places hot mix at construction locations. Compost and seeding activities are getting underway. Expect lane closures on this project that’s adding passing lanes for multiple sections of roadway in both the eastbound and westbound directions. Once the widening is complete, a seal coat and final surface will be applied. A daily construction speed limit of 60 mph is in place when work is being performed.
Farm Road 1253 Widening Project
• Limits: From County Road 462 south, 1.3 miles north of FM 857 south to FM 1805; FM 1804 from Wood County line to US 69; FM 2015 from CR 313 to FM 16
• Contractor: Longview Bridge and Road, Ltd., of Longview
• Cost: $7.5 million
• Anticipated Completion Date: Fall 2016
FM 1804 is scheduled to close at the bridge for about three weeks starting Monday, December 5, for repairs to the Sabine River Bridge and the relief bridge. Meanwhile, lane closures can also be expected on FM 1253 where dirt work continues. No work is schedued for FM 2015. The contract consists of widening, sealing and resurfacing all three roadways.
Spur 248 Widening Project
• Limits: From 1.75 miles west of FM 848/Old Omen Road going east to SH 64 southeast of Tyler
• Contractor: Lonestar Equipment Company, Inc.
• Cost: $8.6 million
• Anticipated Completion Date: Summer 2018
Expect lane closures as storm drain and embankment work continue in the eastbound lanes. The speed limit has been reduced to 55 mph during construction. This project is widening Spur 248 from two lanes to a four-lane divided roadway with flush median.
County Road Bridge Replacement Projects
· Limits: CR 4129 at Mill Creek near Lindale; CR 3104 at Prairie Creek north of FM 1252 near Winona; and CR 2138 at Blackhawk Creek south of Whitehouse
· Contractor: Pierce Construction
· Cost: $947,000.00
· Anticipated Completion Date: Spring 2017
CR 2138 remains closed for several more months as foundation work is conducted on this bridge replacement project. No work is scheduled for CR 4129 and CR 3104. All three roads are closed for the construction of new bridges and approaches.
U.S. Highway 271 Repairs and Resurfacing Project
• Limits: From FM 2015 southward to Oakwood Street/Spur 147 in Tyler
• Contractor: Reynolds & Kay
• Cost: $4.3 million
• Anticipated Completion Date: Fall 2018
Hot mix application and placement of permanent signage continue on this 4.5-mile project to repair and resurface the roadway.
Gregg County – Longview Maintenance plans to conduct hot mix mill and inlay operations on SH 42 in Kilgore between Longview and Lantrip streets. Base repair work is also scheduled for Loop 485 in Gladewater. Crews will also be making bridge joint repairs to the I-20 westbound lanes from SH 322 to SH 31. Expect lane closures at all locations with flaggers providing traffic control.
Gregg County construction projects updates:
FM 2087 over Sabine River
• Limits: 500 feet north of bridge to 500 feet south of bridge
• Contractor: Longview Bridge and Road, Ltd., of Longview.
• Cost: $3.7 million
• Anticipated Completion Date: Summer 2017
The contractor is working on the substructure of the new bridge. Alternate routes have been established to move traffic around FM 2087 at the Sabine River which is closed until summer 2017 for construction of a new bridge. Local traffic is allowed to approach from the north or the south but is not allowed to cross the river. Motorists can take SH 31 from I-20 to Loop 281 or SH 322/SH 149 from I-20 to Loop 281. The project includes the construction of a new bridge and approaches, grading, asphalt concrete pavement base and surface, metal beam guard fence and pavement markings.
FM 2275 George Richey Extension (Segment I)
Limits: McCann Road west to SH 300 (Gilmer Road)
Contractor: East Texas Bridge, Inc.
Cost: $12.4 million
Anticipated Completion Date: Fall 2017
Current work includes hauling embankment, laying storm drains and other preparations for building the bridge on this new roadway to connect Gilmer and McCann roads. This Segment I project includes constructing two bridges and a four-lane roadway with center left turn lanes from McCann Road to SH 300/Gilmer Road. Excavation, embankment, bridge construction, subgrade treatment, storm drains, hot mix asphalt, curb and gutter and sidewalk are all part of the new construction.
FM 2275 George Richey Extension (Segments II & III)
• Limits: McCann Road to US 259
• Contractor: East Texas Bridge, Inc.
• Cost: $12.8 million
• Anticipated Completion Date: Fall 2016
While this portion of FM 2275/George Richey Road is open to traffic work continues with installation of metal beam guard fence at the bridge and closeout activities between US 259 and McCann Road. The project is constructing a new roadway from McCann Road to US 259.
Loop 281 at FM 2087 Overpass
• Limits: SH 31 to approximately one mile south of SH 31
• Contractor: Longview Bridge and Road, Ltd., of Longview.
• Cost: $13.2 million
• Anticipated Completion Date: March 2017
The turnaround under the bridge opened to traffic but drivers should still exhibit caution through this work zone as the contractor continues other work including the installation of illumination, traffic signal, curb and gutter, inlets, embankment, building a new exit ramp for SH 31, and paving. This project is building a new overpass over the railroad crossing. Expect lane closures.
Anderson County – Palestine Maintenance plans to conduct pavement work at various locations on FM 321 between US 287 and SH 19. Expect lane closures with flaggers providing traffic control.
Anderson County construction projects updates:
US 79 New Lane Construction Project
• Limits: 1.6 miles southwest of Loop 256 in Palestine south to the Trinity River
• Contractor: Longview Bridge and Road, Ltd., of Longview.
• Cost: $42.7 million
• Anticipated Completion Date: Spring 2018
Work gets underway at the intersection of FM 294 and US 79 with lane changes where periodic closures should be expected. The contractor is currently placing embankment for the new northbound bridge as well as conducting culvert work under the existing northbound US 79 lanes at Trucker. Motorists using FM 645 are reminded that US 79 traffic does not stop at the intersection as work continues on the detour at the northbound ramp. Other work continues from CR 2205 to just south of FM 645. The contractor is working on detours in the area of FM 645 at Tucker. This project expands a 5.3 mile section of US 79 from two lanes to a four-lane divided highway with a continuous left turn lane and a depressed median. Work started in November 2012.
SH 19 Widening Project
Limits: 3.6 miles north of FM 837 (Henderson Co. line) south to .4 mile north of FM 321 at Montalba
• Contractor: Big Creek Construction of Hewitt
• Cost: $12.5 million
• Anticipated Completion Date: Summer 2017
Widening activities continue on the southbound lanes. The contractor continues to work on culvert extensions, driveways and temporary lane widening throughout the project limits. Expect occasional lane closures with flaggers and a pilot car providing traffic control. The posted speed limit is 55 mph.
Off-System Bridge Replacement Project
Limits: County Road (CR) 471 at Box Creek; CR 4801 at Indian Creek; CR 1231 at Stills Creek
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $817,412.15
Anticipated Completion Date: Fall 2016
The contractor continues to conduct closeout activities on this project with the bridges open to traffic.
Off-System Bridge Replacement Project
Limits: County Road (CR) 2133 at Mack Creek between US 79 and FM 1990
Contractor: Fritcher Construction Services of Tyler
Cost: $499,832.22
Anticipated Completion Date: Early 2017
Work continues to progress on this bridge replacement project with the road closed to traffic and detours in place.
Cherokee County – Jacksonville Maintenance resumes edge repairs on FM 747S while the Rusk crew conducts base repair work on US 84W at the Neches River; on FM 1819; and on US 84 east of US 69 in the curb and gutter section. Expect lane closures with flaggers providing traffic control.
Cherokee County construction projects updates:
US 69 Widening and Resurfacing
Limits: From Loop 456 in Jacksonville going south to just north of Loop 62 in Rusk
Contractor: Madden Contracting Company, LLC
Cost: $11 million
Anticipated Completion Date: Summer 2016
No work is planned for this project which is widening US 69 by adding 2’ edge treatment and resurface the road.
US 69 Widening and Resurfacing
Limits: From 0.028 mile south of FM 343 in Rusk southward to just north of SH 21 in Alto
Contractor: Madden Contracting Company, LLC
Cost: $9.3 million
Anticipated Completion Date: Fall 2016
Paving operations are being conducting on this job that’s widening and resurfacing US 69. Expect lane closures.
US 79 Repairs and Resurfacing Project
Limits: From SH 204 to Mud Creek
Contractor: Reynolds & Kay
Cost: $5.7 million
Anticipated Completion Date: Summer 2017
Work on the subgrade is being conducted in the eastbound lanes on this project to repair and resurface the roadway. Remember the speed limit has been reduced and traffic fines double when workers are present.
FM 22 and FM 23 Widening Project
Limits: From US 69 south of Jacksonville going SW to 1.5 miles west of FM 768 (Gallatin area); FM 23 from FM 343 to FM 1857
Contractor: Madden Contracting Company, LLC
Cost: $8.5 million
Anticipated Completion Date: Fall 2016
Cleanup activities continue on FM 23. These are safety projects designed to widen the roadways from 20’ to 24’ along a 4.2-mile section.
County Road Bridge Replacement Projects
Limits: CR 1707 at One Arm Creek west of Rusk between FM 347 and FM 2138 and CR 2303 at One Eye Creek south of Rusk between FM 23 and FM 752
Contractor: Stateline Construction
Cost: $699,993.90
Anticipated Completion Date: Winter 2016
Cleanup activities set to begin on CR 1707 and CR 2303. Both roads are closed as new bridges and approaches are built. The closures are planned to last about six months.

Henderson County – Athens Maintenance plans to continue overlay operations and level up work on FM 2613 between FM 85 and the Kaufman County line. Crews will also be conducting fog seal operations on several roadways including FM 1615, Loop 60, FM 1803 from SH 31 to FM 317; and on FM 85 from SH 274 to FM 2613. Expect lane closures with flaggers providing traffic control.
Henderson County construction projects updates:
US 175 Widening Project (Phase I)
Limits: 0.1 miles southeast of FM 804 near Baxter southeast to 1.1 miles east of Loop 60E at Larue
Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
Cost: $39.2 million
Anticipated Completion Date: November 2018
Expect short delays as work gets underway at the RM 2588 intersection in LaRue where the contractor will be removing pavement from US 175 for about 1,000 feet southward. A short segment of US 175 will remain unpaved while work continues at the intersection. Meanwhile, drivers should expect one lane carrying two-way traffic throughout the project limits as well as occasional daytime lane closures at various locations. Work continues to progress with traffic moved to the new alignment between the west end of Loop 60 to approximately one mile east of the loop. The eastern portion of Loop 60 remains closed for construction of the new westbound mainlanes on this project that expands US 175 from two lanes to a four-lane divided with a depressed median. Dirt and drainage work around Loop 60E in Larue to near Baxter is ongoing. The speed limit in the construction zone has been set at 55 mph so slow down because traffic fines double when workers are present. Phase I construction started April 6, 2015.
US 175 Widening Project (Phase II)
Limits: 1.1 miles east of Loop 60B at LaRue to 0.85 mile east of FM 315 at Poynor
Contractor: Sundt Construction, Inc., of San Antonio
Cost: $37.8 million
Anticipated Completion Date: Late Summer 2017
Night work is ongoing between 5 a.m. and 11 p.m., Monday–Friday. The contractor is conducting work on the bridge overpass in the eastbound and westbound travel lanes at FM 315S as well as the horseshoe lake bridges. Dirt work continues around Poynor schools and several other locations as does drainage work. As part of the new highway construction, a short stretch of CR 4401 has been permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 remains open with access from CR 4345/Camp Road.
This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.
US 175 Widening Project (Phase III)
Limits: 0.85 miles east of FM 315 in Poynor, southeast to .5 miles NW of SH 155 at Frankston
Contractor: A.L. Helmcamp, Inc.
Cost: $27.6 million
Anticipated Completion Date: Spring 2019
The contractor continues to install and maintain storm water control measures throughout the project limits as well as install drainage box culverts west of CR 301. Work also continues on the culvert wing wall. Earthwork operations are also underway. Lane closures are possible. This project is expanding US 175 from two lanes to a four-lane divided highway with a depressed median.
FM 315/FM 1616 Widening Project
Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
Contractor: Big Creek Construction, LTD, of Hewitt, Texas
Cost: $3.07 million
Anticipated Completion Date: Fall 2016
Mobile operations have been implemented as temporary centerline striping is applied. Work on FM 1616 is ongoing. FM 315 is complete.
SH 31 Bridge Painting Project – Westbound at Trinity River/Eastbound at Cedar Creek
Limits: From just east of Cedar Creek to just west of the Trinity River
Contractor: Olympus Painting Contractors Inc., of Clearwater, Florida
Cost: $2.3 million
Anticipated Completion Date: Fall 2016
Work resumes under the westbound Trinity River Bridge to correct erosion problems. Motorists should expect periodic lane closures in the westbound outside travel lane on the west end of the river bridge.
Rusk County – Henderson Maintenance plans to perform base repairs on FM 1798 from FM 225 to FM 839. Expect the roadway to be reduced to one lane carrying two-way traffic with flaggers and a pilot car guiding traffic through the work zone.
Rusk County construction projects updates:
US 259 North Project
Limits: From Star to Loop 571
Contractor: Madden Contracting Company, LLC
Cost: $4.3 million
Anticipated Completion Date: Fall 2016
The contractor is placing the final striping on this project so alternating lane closures and delays can be expected. This 2.3 mile project includes base repairs, mill and inlay of asphalt surface, applying a hot mix overlay, and upgrading the pavement markings.
US 79 South Project
Limits: From Loop 571 in Henderson going southwest for 3.0 miles to FM 839
Contractor: Drewery Construction Co., Inc.
Cost: $6.7 million
Anticipated Completion Date: Summer 2017
Embankment is being placed on the widened edges of this portion of US 79. Watch for moving equipment near the edge of the travel lanes. Expect lane closures and delays with one-way traffic control. Flaggers and a pilot car will guide traffic through the work zone. The posted speed limit has been reduced to 60 mph throughout this work zone and is being enforced by DPS. The project includes widening the existing pavement and adding a center left turn lane resulting in a new asphalt surface when the job is completed.
FM 3135 Widening Project
Limits: 1.9 miles NE of US 79 (W of CR 222) north to 1.7 miles SW of FM 1251 (CR 262)
Contractor: Madden Contracting Company, LLC
Cost: $2 million
Anticipated Completion Date: Fall 2016
No work is scheduled for this project that consists of widening the pavement and installing milled centerline rumble strips on a three-mile section of roadway.
FM 95 Widening Project
Limits: FM 1798 to SH 315
Contractor: Madden Contracting Company, LLC
Cost: $2.5 million
Anticipated Completion Date: Fall 2016
No work is scheduled for this project that is widening a four-mile section of the road and adding shoulders.
SH 43 Overlay Project
Limits: From four miles south of FM 2658 to FM 3231
Contractor: Madden Contracting Company, LLC
Cost: $4.6 million
Anticipated Completion Date: Fall 2016
Metal beam guard fence is being installed on this project. Expect alternating lane closures with flaggers and a pilot car providing traffic control. The project consists of placing an asphalt overlay on the roadway, base repairs, and new metal beam guard fence.
Van Zandt County – Canton Maintenance plans to address routine maintenance issues around the county. Expect lane closures with flaggers providing traffic control.
Van Zandt County construction projects updates:
SH 198 Widening Project
Limits: from SH 243 in Canton southwest to 0.4 miles northeast of FM 316 near Phalba
Contractor: Big Creek Construction, Ltd., of Waco
Cost: $5 million
Anticipated Completion Date: Fall 2016
Final cleanup operations resume as does work to backfill pavement edges on this widening job. Expect lane closures with flaggers providing traffic control.
FM 316 Widening Project
Limits: From FM 1256 south to FM 3080
Contractor: Big Creek Construction, Ltd., of Hewitt
Cost: $255,474.00
Anticipated Completion Date: Fall 2016
No work is scheduled on this project to widen the roadway, and install safety end treatments and advance warning signs.
FM 314 Widening Project
• Limits: from I-20 to the Van Zandt/Henderson County line
• Contractor: A.L. Helmcamp, Inc., of Buffalo
• Cost: $11.9 million
• Anticipated Completion Date: Summer 2018
No work is planned for this week.
FM 1256 Widening Project
• Limits: from FM 316 eastward to SH 19
• Contractor: Longview Bridge and Road, Ltd.
• Cost: $5.8 million
• Anticipated Completion Date: Fall 2018
The contractor is extending the structures on both sides of the road on this project that is widening almost eight miles of the roadway. Expect lane closures with flaggers providing traffic control.
County Roads Bridge Replacement Projects
• Limits: CR 3105 at Crooked Creek, CR 3809 at Negro Creek, CR 4404 at Cream Level Creek, and CR 2908 at Purtis Creek
• Contractor: Stateline Construction, LLC.
• Cost: $1.4 million
• Anticipated Completion Date: Summer 2017
The contractor is currently removing the existing bridge on CR 3105 at Crooked Creek and construction of the new bridge underway. The roadway is closed to thru traffic. CR 3809 at Negro Creek is open to thru traffic.
I-20 Westbound Exit Relocation Project
• Limits: FM 314 WB Exit Ramp and Frontage Road
• Contractor: Longview Bridge and Road, Ltd.
• Cost: $4.6 million
• Anticipated Completion Date: Summer 2017
Current work includes extending drainage structures and installing storm water control measures on this I-20 project to relocate the I-20 WB Exit Ramp at FM 314 and reconstruct the frontage road. No lane closures are expected on I-20. Phase I of the project includes reconstructing the frontage road and building the new exit ramp 1.13 miles east of FM 314. This requires closing a portion of the frontage road for several months from approximately 500 feet east of the current exit ramp to about 3,250 feet eastward. The existing ramp and frontage road from the ramp west to FM 314 will remain open during this phase of work. Phase II will consist of constructing a detour from the FM 314 intersection eastward for about 2,000 feet, and completing the frontage road west to the intersection.
Wood County – Mineola Maintenance plans to conduct pavement level up work on FM 3056, FM 1254 and FM 2225. Expect lane closures with flaggers directing traffic at all locations.
I-20 Total Maintenance Contract
Limits: Gregg, Smith and Van Zandt counties
Contractor: Fireman Excavating
Routine maintenance activities are ongoing on I-20 with moving operations throughout the week:
– Debris Removal: Monday from the inside lane through all three counties
– Debris Removal: Tuesday from the outside lane through all three counties
– Luminaire Maintenance: Monday/Wednesday through all three counties
– Guardrail Maintenance: Tuesday/Wednesday through all three counties
No lane closures planned but that is subject to change.



News Partner
Advertisement
Advertisement Advertisement

 
Advertisement
Advertisement

© 1999 - 2024 Copyright ATW Media, LLC