TxDOT Project Updates for the Week of July 17

Posted/updated on: July 18, 2017 at 3:07 am
Print Friendly, PDF & Email


TYLER – Here’s a look at work planned in the district during the Week of July 17, 2017. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Slow down and pay attention when traveling through work zones.

The SH 64 resurfacing project continues from Loop 323 to just west of the Tyler Pounds Airport. Seal coat operations kick off Monday, July 17, and include lane closures with possible delays for traffic. Motorists are urged to avoid the area if at all possible during this work. Flaggers will provide traffic control. More project information is available in the Smith County section of this news release.

Milling operations start Monday, July 17, on the SH 31E overlay project between Loop 323 and FM 850 in Tyler. Motorists should allow extra time to reach their destinations as work is conducted in the eastbound lanes starting at Loop 323. More project information is available in the Smith County section of this release.

A major traffic switch is planned for Wednesday, July 19, on the US 175 construction project from Baxter to LaRue in Henderson County. Traffic will be moved from the existing two-lane structure to the newly completed lanes on the south side of the corridor. In addition to the changes to US 175, local residents and county road traffic may see alterations in the way they enter onto the new lanes. This new but temporary configuration will remain in place for about a year as the old lanes are re-worked. Caution is advised as traffic acclimates to these changes. The speed limit has been reduced to 55 mph in this work zone. Additional project information is available in the Henderson County section of this release.

Motorists should prepare for a night time project set to get underway on US 271 on Sunday, July 23, in Tyler. The project consists of repairing the base in the mainlanes, conducting work on the side streets, applying a new surface and striping. This work will have major impacts on traffic flow. Law enforcement will be utilized to assist with traffic control. Special attention is being given to allow for minimal impacts to hospitals and the flow of emergency vehicles. Work will be conducted from 7:30 p.m. to 6 a.m., Sunday through Thursday nights. Expect lane closures and delays during this work. Get additional project information in the Smith County section of this release.

SMITH COUNTY – Tyler Maintenance plans to conduct base repairs on FM 14 near the Wood County line and edge repairs on FM 346 east of Whitehouse southward toward Troup. Expect lane closures with flaggers providing traffic control at both locations.

Smith County construction projects updates:

US 271 Mill and Inlay Project (New Project)

Limits: From 0.4 miles south of Spur 147/Oakwood St., south to SH 64/Fifth St. in Tyler
Contractor: Clark Construction of Texas, Inc. from San Antonio
Cost: $2.1 million
Anticipated completion date: Fall 2017

This new night time construction project is set to begin at 7:30 p.m., Sunday, July 23. Message boards have been installed along the project limits to notify the traveling public about the project. The contract consists of base repairs, planing, applying a hot mix surface and striping. Work will be conducted between 7:30 p.m. and 6 a.m. Alternate routes are suggested to avoid lane closures and delays during work hours.

FM 344 Culvert Replacement Project

Limits: At Bell Branch Creek (approximately 1 mile west of SH 110)
Contractor: Red Baron Building Company, LLC
Cost: $348,000
Anticipated completion date: Summer 2017

Concrete work continues on the culvert on FM 344 at Bell Branch Creek near Whitehouse. The job also includes restoring the pavement. The roadway is closed at this location and motorists must use other routes to reach their destinations. A detour route is in place: take FM 756 to FM 346 to SH 110.

FM 1253 Widening Project

Limits: From County Road 462 S, 1.3 miles N of FM 857 S to FM 1805; FM 1804 from the Wood County line to US 69; FM 2015 from CR 313 to FM 16
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $7.5 million
Anticipated Completion Date: Summer 2017

No lane closures are anticipated as work continues to widen, seal and resurface the roads.

SH 31E Widening Project

Limits: From FM 757 to FM 2012
Contractor: Reynolds & Kay, LTD
Cost: $7.8 million
Anticipated Completion Date: Summer 2017

No work is currently scheduled to occur. When work resumes, the contractor will be applying the Porous Friction Course (PFC) surface which will cause delays for drivers. The speed limit during work hours is 60 mph.

SH 31E Overlay Project

Limits: From Loop 323 to FM 850
Contractor: Reynolds & Kay, LTD
Cost: $1.8 million
Anticipated Completion Date: Summer 2017

Milling operations begin Monday, July 17, in the eastbound lanes at the intersection of Loop 323. Message boards are in place to notify the traveling public of the work. This project is expected to begin soon to place a one course surface treatment and a new Porous Friction Course (PFC) surface on the roadway.

Spur 248 Widening Project

Limits: From 1.75 miles west of FM 848/Old Omen Road going east to SH 64 southeast of Tyler
Contractor: Lonestar Equipment Company, Inc.
Cost: $8.6 million
Anticipated Completion Date: Summer 2018

Work continues on the eastbound lanes including storm drain, flex-base and cement treating. Expect lane closures with flaggers providing traffic control. The speed limit is 55 mph during construction to widen Spur 248 from two lanes to a four-lane divided roadway with flush median.

SH 64 Resurfacing Project

Limits: From Loop 323 to 0.7 mile west of FM 724
Contractor: IOC Company of Edinberg, TX
Cost: $1.7 million
Anticipated completion date: Summer 2017

Motorists can expect lane closures and delays as the contractor conducts seal coat operations starting Monday. Work will be conducted in the eastbound lanes moving toward Tyler. The contract is placing a new Porous Friction Course (PFC) surface on the roadway from Loop 323 to just past Tyler Pounds Airport. Flaggers will provide traffic control.

SH 155 Resurfacing Project

Limits: From 2.0 miles south of US 80 (Upshur C/L), south to I-20
Contractor: Madden Contracting Company, LLC
Cost: $9.3 million
Anticipated completion date: Summer of 2017

No work is planned this week. The project is repairing the existing pavement structure and placing a new Porous Friction Course (PFC) surface.

I-20 Resurfacing Project

Limits: From US 69 to FM 14 WB only
Contractor: Clark Construction
Cost: $2.9 million
Anticipated completion date: Summer 2017

No work is scheduled on this project to place a new Porous Friction Course (PFC) surface in the westbound lanes and install updates to the metal beam guard fence along this stretch of I-20.

Turn Lanes Project

Limits: Various locations throughout Tyler
Contractor: Lonestar Equipment Company, Inc.
Cost: $2.4 million
Anticipated Completion Date: Summer 2018

Work continues on Loop 323 between Old Bullard Road and Donnybrook Avenue on this project to add right turn lanes to various intersections in Tyler. The contractor is removing portions of the existing medians to make upgrades to the existing turn lanes. Work will be conducted on US 69, Cumberland Road, Independence, South Donnybrook, Rice, South Town and wrap up at Grande and FM 2493. Expect lane closures and delays during this work with flaggers providing traffic control.

GREGG COUNTY – Longview Maintenance will be milling and inlaying asphalt patches on SH 300 around the Reel Road area. Expect various lane closures and delays with flaggers providing traffic control.

Gregg County construction projects updates:

US 80 Widening in Gladewater

Limits: Loop 485 to Locker Plant Road.
Contractor: Longview Bridge and Road
Cost: $3.538 million
Anticipated Completion Date: Spring 2018

The contractor is working on storm sewer on the south side of the roadway. Traffic is reduced to one lane as Phase I work is conducted. The project consists of widening US 80 to four through lanes with a left turn lane from Loop 485 to Locker Plant Road. Work includes earthwork, base and surface work, storm sewer, concrete curb and gutter, safety improvements, and upgrading signage and pavement markings. Motorists can expect delays and lane closures during this work.

Loop 281 at FM 1845/Pine Tree Road

Limits: From US 80 to Shofner Drive
Contractor: Longview Bridge and Road, Ltd., of Longview.
Cost: $4.54 million
Anticipated Completion Date: January 2018

Traffic is now in the Phase II configuration with the roadway reduced to one lane in all directions. Work is being conducted in multiple traffic phases that could require overnight lane closures. Motorists should use other routes to avoid delays. The project includes widening the roadway, installing storm drain, grading and base work, curb and gutter, raised medians, surface, signs and pavement markings.

Loop 281 at FM 2087 Overpass

Limits: From SH 31 to approximately one mile south of SH 31
Contractor: Longview Bridge and Road, Ltd., of Longview.
Cost: $13.2 million
Anticipated Completion Date: Summer 2017

The contractor is conducting closeout activities on this project to build a new overpass over the railroad crossing.

FM 2087 over Sabine River

Limits: From 500 feet north of bridge to 500 feet south of bridge
Contractor: Longview Bridge and Road, Ltd., of Longview.
Cost: $3.7 million
Anticipated Completion Date: Late Summer 2017

Work on the new bridge railing is ongoing. Alternate routes have been established to move traffic around FM 2087 at the Sabine River which is closed until late summer 2017 for construction of a new bridge. Local traffic is allowed to approach from the north or the south but is not allowed to cross the river. Motorists can take SH 31 from I-20 to Loop 281 or SH 322/SH 149 from I-20 to Loop 281. The project includes the construction of a new bridge and approaches, grading, asphalt concrete pavement base and surface, metal beam guard fence and pavement markings.

FM 2275 George Richey Extension (Segment I)

Limits: From McCann Road west to SH 300 (Gilmer Road)
Contractor: East Texas Bridge, Inc.
Cost: $12.4 million
Anticipated Completion Date: Fall 2017

The contractor is hauling embankment, laying storm drains and building the new bridge. The project includes constructing two bridges and a four-lane roadway with center left turn lanes from McCann Road to SH 300/Gilmer Road. The job includes applying a hot mix asphalt surface, curb and gutter as well as sidewalk.

Anderson County – Palestine Maintenance continues base and edge repairs on FM 323 between SH 294 and FM 1817. Expect lane closures with flaggers providing traffic control.

Anderson County construction projects updates:

US 79 New Lane Construction Project

Limits: From 1.6 miles southwest of Loop 256 in Palestine south to the Trinity River
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $42.7 million
Anticipated Completion Date: Fall 2017

Work continues in the existing northbound lanes with hot mix level up to be followed by surface mix. Motorists are urged to watch for trucks entering and exiting the traffic flow. Other ongoing work includes: concrete paving operations in the new northbound lanes between FM 645 and CR 2205, and work on the new FM 645 Overpass. The project is expanding a 5.3 mile section of US 79 from two lanes to a four-lane divided highway with a continuous left turn lane and a depressed median.

SH 19 Widening Project

Limits: From 3.6 miles N of FM 837 (Henderson Co. line) south to .4 mile N of FM 321 at Montalba
Contractor: Big Creek Construction of Hewitt
Cost: $12.5 million
Anticipated Completion Date: Winter 2017

Work continues to widen the northbound lanes by adding shoulders and passing lanes. The posted speed limit is 55 mph. Expect delays and multiple lane closures with flaggers and a pilot car providing traffic control.

Off-System Bridge Replacement Project

Limits: County Road (CR) 2133 at Mack Creek between US 79 and FM 1990
Contractor: Fritcher Construction Services of Tyler
Cost: $499,832.22
Anticipated Completion Date: Summer 2017

The road is closed and traffic is detoured for the construction of a new bridge at Mack Creek on CR 2133. Work continues with dirt work, hot mix asphalt, and metal beam guard fence scheduled over the next couple of weeks. The bridge should be open to traffic by the mid-August, weather permitting.

Off-System Bridge Replacement Project

Limits: County Road 458 at Beaver Creek and County Road 2418 at Otter Creek
Contractor: Longview Bridge and Road Ltd. Of Longview
Anticipated Completion Date: Winter 2017

County Road (CR) 458 is closed and construction is ongoing to build the new bridge. Only local traffic has access between Beaver Creek and CR 459 and from Beaver Creek to FM 2330.

Cherokee County – Jacksonville and Rusk Maintenance move the mill and inlay operation to US 84 between FM 2138 and the Neches River. Expect lane closures with flaggers providing traffic control.

Cherokee County construction projects updates:

US 69 Widening through Wells

Limits: From 2 miles north of FM 1247 in Wells, south to 0.9 mile south of FM 1247
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $17.6 million
Anticipated Completion Date: Summer 2018

Work to build a detour and install culverts is ongoing on this project to widen US 69 through Wells from two lanes to four lanes with new curb and gutter and a two-way left turn lane through town. The speed limit has been reduced on the northern end of the project and will remain in effect until construction is complete.

US 79 Repairs and Resurfacing Project

Limits: From SH 204 to Mud Creek
Contractor: Reynolds & Kay
Cost: $5.7 million
Anticipated Completion Date: Summer 2017

Work continues to place the new final surface on the roadway. The contractor also plans to start installing hot mix driveways along the project limits. Expect daily lane closures for the duration of the project when construction equipment is near the travel lanes. The speed limit is reduced throughout the project limits.

FM 22 Safety Treatment Project

Limits: From 1.5 MI W of FM 768, E to SH 110
Contractor: Highway 19 Construction
Cost: $1 million
Anticipated completion date: Fall 2017

Drainage work continues on this project to treat fixed objects for safety. Expect lane closures.

Henderson County – Athens Maintenance plans to conduct edge repairs on FM 607 from SH 31 to FM 317. Spot milling operations will be performed on FM 3079 from FM 315 to FM 314. Expect lane closures with flaggers providing traffic control.

Henderson County construction projects updates:

US 175 Widening Project (Phase I)

Limits: From 0.1 mile SE of FM 804 near Baxter SE to 1.1 miles E of Loop 60E at LaRue
Contractor: A.L. Helmcamp, Inc. and Big Creek Construction
Cost: $39.2 million
Anticipated Completion Date: November 2018

A traffic switch to move traffic temporarily to the newly constructed southbound lanes is set for Wednesday, July 19. The switch will occur from FM 804 near Baxter, east to 1.1 miles east of Loop 60 at LaRue. This will allow the contractor to re-work the old US 175 mainlanes. These changes could also alter the way local residents and county road traffic enters the new lanes. Expect lane closures and delays on this project. Look for message boards and other advance warning signage already installed. Caution is advised as traffic acclimates to the changes. Traffic will remain in this configuration until work on the existing roadway is completed, approximately one year, weather permitting. The speed limit is 55 mph on this project to expand US 175 from two lanes to a four-lane divided highway with a depressed median.

US 175 Widening Project (Phase II)

Limits: From 1.1 miles E of Loop 60B at LaRue to 0.85 mile E of FM 315 at Poynor
Contractor: Sundt Construction, Inc., of San Antonio
Cost: $37.8 million
Anticipated Completion Date: Late Summer 2017

The permanent westbound travel lanes are under construction with the contractor extending concrete structures and conducting dirt work as phase two construction progresses. As part of the new highway construction, a short stretch of CR 4401 was permanently closed from the intersection of US 175’s new eastbound lanes to the new right of way. The rest of CR 4401 is open with access from CR 4354/Camp Road.

This Phase II project will expand US 175 from two lanes to a four-lane divided with a depressed median. Drivers should anticipate two-way traffic throughout the project limits which stretch 4.7 miles ending just east of FM 315 in Poynor. The speed limit has been set at 55 mph. A portion of this phase is being built on new location around the south side of Poynor. This, like Phase I, is a mobility project to add capacity and improve safety, and includes adding one lane in each direction.

US 175 Widening Project (Phase III)

Limits: From 0.85 mile E of FM 315 in Poynor SE to .5 mile NW of SH 155 at Frankston
Contractor: A.L. Helmcamp, Inc.
Cost: $27.6 million
Anticipated Completion Date: Spring 2019

The contractor is installing drainage box culverts and maintaining storm water control measures throughout the project limits. Earth and culvert wing wall work, and flex-base operations are ongoing. Lane closures are possible on this project that’s expanding US 175 from two lanes to a four-lane divided highway with a depressed median.

FM 315/FM 1616 Widening Project

Limits: From FM 314S to CS End at County Road 4325, 4224, etc.
Contractor: Big Creek Construction, LTD, of Hewitt, Texas
Cost: $3.07 million
Anticipated Completion Date: Summer 2017

Work on closeout activities continues on this project.

Rusk County – Henderson Maintenance plans to perform edge maintenance on FM 850 from US 259 to FM 2276. Expect lane closures with flaggers and a pilot car providing traffic control.

Rusk County construction projects updates:

US 79 South Widening Project

Limits: From Loop 571 in Henderson going southwest for 3.0 miles to FM 839
Contractor: Drewery Construction Co., Inc.
Cost: $6.7 million
Anticipated Completion Date: Summer 2017

Striping and shoulder embankment work are ongoing. Expect lane closures and brief delays with flaggers and a pilot car providing traffic control. A reduced speed limit of 60 mph is implemented and is being enforced by DPS. The project includes widening the existing pavement and adding a center left turn lane resulting in a new asphalt surface when the job is completed.

SH 43 Overlay Project

Limits: From US 79 (at the Star) to 9.9 miles toward Tatum at CR 2136
Contractor: Madden Contracting Company, LLC
Cost: $4.6 million
Anticipated Completion Date: Fall 2017

Hot mix asphalt operations are ongoing. Expect alternating lane closures and delays with flaggers and a pilot car providing traffic control. The project includes applying an asphalt overlay, base repairs, applying new striping, and installing new metal beam guard fence.

ADA Ramp Installations

Limits: In Overton – SH 135 from SH 323 to McKay St; FM 850 from Rusk St. to Neal St.
Limits: In Henderson – Business 64/Marshall Ave. from Van Buren St. to Redbud St.; Business 79/Main St. from College St. to Oak Street; FM 13/West Main St. from Standish St. to Jackson St.
Contractor: Ti-Zack Concrete, Inc., of Minnesota
Cost: $1.4 million
Anticipated Completion Date: Late Summer 2017

Work continues to construct ADA curb ramps on SH 135 and FM 850 in Overton. Work is planned for locations around Rusk County including Business 79 in Henderson where the next work is scheduled. The project limits are basically the downtown areas of Henderson and Overton. Expect outside lane closures in alternating directions as the work progresses. Delays are possible. Work includes removing the existing and building new ramps, sidewalks, hand rails and curb and gutter.

Van Zandt County – Canton Maintenance continues overlaying SH 198 from the Kaufman County line moving toward Canton. Expect lane closures with flaggers providing traffic control.

Van Zandt County construction projects updates:

I-20 Westbound Exit Relocation Project

Limits: From FM 314 WB Exit Ramp and Frontage Road
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $4.6 million
Anticipated Completion Date: Summer 2017

No work will be conducted this week.

Phase I of the project includes reconstructing the frontage road and building a new exit ramp 1.13 miles east of FM 314. This requires closing a portion of the frontage road for several months from approximately 500 feet east of the current exit ramp to about 3,250 feet eastward. The existing ramp and frontage road from the ramp west to FM 314 will remain open during this phase of work. Phase II will consist of constructing a detour from the FM 314 intersection eastward for about 2,000 feet, and completing the frontage road west to the intersection.

FM 314 Widening Project

Limits: From I-20 to the Van Zandt/Henderson County line
Contractor: A.L. Helmcamp, Inc., of Buffalo
Cost: $11.9 million
Anticipated Completion Date: Summer 2018

Structure work will continue at Horsley Creek. Subgrade work and cement treating will begin on the next section of roadway, approximately four miles south of I-20. Expect delays with daily lane closures controlled by flaggers and a pilot vehicle.

FM 1256 Widening Project

Limits: From FM 316 eastward to SH 19
Contractor: Longview Bridge and Road, Ltd., of Longview
Cost: $5.8 million
Anticipated Completion Date: Fall 2018

Work continues to pave driveways and mailbox turnouts. Flex base will be finalized and the prime course surface treatment applied from two miles east of FM 316. Expect daily lane closures with flaggers and a pilot vehicle providing traffic control on this project to widen almost eight miles of the roadway.

FM 1861 Project

Limits: From SH 19 to FM 2339
Contractor: A.L. Helmcamp, of Buffalo, TX
Cost: $2.44 million
Anticipated Completion Date: September 2017

Roadway rehab operations will be conducted with the contractor milling and cement treating flex-base. Structure work is ongoing. Expect lane closures with flaggers and a pilot vehicle handling traffic control.

County Roads Bridge Replacement Projects

Limits: CR 3105 at Crooked Creek, CR 3809 at Negro Creek, CR 4404 at Cream Level Creek, and CR 2908 at Purtis Creek
Contractor: Stateline Construction, LLC.
Cost: $1.4 million
Anticipated Completion Date: Summer 2017

All roadways are open to thru traffic as the contractor continues final cleanup activities.

Wood County – Mineola Maintenance will conduct seal coat work on Loop 564 and SH 37. Expect lane closures in both work zones with flaggers providing traffic control.

Wood County construction projects updates:

SH 182, etc., Safety Treating Project

Limits: Various Roads – Current work on FM 2869 from FM 2088 south 8.12 miles to FM 49

Contractor: Highway 19 Construction, LLC.
Cost: $1.2 million
Anticipated Completion Date: July 2017 for FM 2869; February 2018 for all work

The contractor continues driveway repairs on FM 2869 with no impacts to traffic. The project includes resetting driveway pipe, cross culvert extensions, guardrail and various other improvements. Current work is on FM 2869 moving southward from FM 2088 to SH 154.